Constituent Date Processing not working

My constituent date from processing on IOM is not working... I have the setting to update existing constituent code with date processing - update date from if existing value is older. However, it is not doing that - old constituents giving new gifts are being updated with the new gift date as the constituent date from. Attached is a screenshot of the setting. 

image



Hi Joanne,

Do you also have the constituent code date from mapped in Field Map or Virtual Fields, or is this the only place where you're specifying the date?

Thank you,
Amanda
Omatic Support
Amanda,

Yes, I have the constituent code date mapped in Field Map. Not in Virtual Fields, though.

Joanne
Hi Joanne,

Because you have the option to update the date from to the processing date selected, try setting the date from in Field Map to Ignore and see if you're getting the desired results.

Please let me know if it still seems to be working incorrectly.

Thank you,
Amanda